Contract Award

Contracts won for Frontier's 8,500 BPSD vacuum distillation unit, Iraq

January 3, 2021

Frontier Company's refinery complex at Arbat, Iraq, at night

Article

Overview

Installation, commissioning and three months' operations support for one train of an 8,500 BPSD vacuum distillation unit and its utilities at Arbat.

SPEC has received contracts from Frontier Company for one train of an 8,500 BPSD vacuum distillation unit and its associated utilities at Arbat, Iraq.

The scope covers installation and commissioning of the unit, together with engineering, construction management and three months of operations and maintenance management following start-up.

Next step

Talk to our engineering team.

Share a process requirement or project enquiry and our engineers will come back to you.

Contact our team

Skid with two horizontal separators, actuated valves and instrument piping