Chacher gas field, Pakistan

Overview
Design, detailed engineering, fabrication and commissioning of a 30 million cubic feet a day sour gas processing facility with 7,500 barrels a day of condensate stabilisation for Tullow Pakistan.
Client
Tullow Pakistan Ltd
Location
Chacher gas field, Pakistan
Country
Pakistan
Capacity
30 million cubic feet a day
Project type
Gas Processing
Completion
2007
Delivery
SPEC's scope included the design, detailed engineering, fabrication and commissioning of the gas processing facility for Tullow Pakistan at the Chacher gas field: 30 MMSCFD of sour gas with 7,500 BPD of condensate.
Scope of supply: skid-mounted three-phase production separator and test separator, 30 MMSCFD amine sweetening facility, 30 MMSCFD TEG dehydration facility, heat medium package, incinerator unit, DCS, chemical injection skids, sour water system, instrument air system, HP and LP flare systems, metering skid, water bath oil heater, crude oil stabilisation column with internals and two crude oil transfer pump skids.